The scope of work is summarised as below: a) 2600 house connections between the new distribution pipeline and the subscribers” water meter using PE pipes with diameter DN32 to DN 110 and 15.600 m house connection pipe li…
ne per an average connection length of approximately 6 m b) Functional SCADA system consisting of computer hardware and software in compliance with the existing SCADA system of the End Recipient c) Construction of 16 underground flowmeters, 1 PRV chamber fitted and 7 Residual Chlorine Measurement Eq
uipment d) Construction of additional water distribution network pipelines diameter DN110 to DN 225 ( appr. 48.500 m ) and DN250 to DN630 (appr.1500m) e) Construction of 9000 m water mains DN 630 and DN1000 f) Construction of total 18 under