- 062071-2026
Wiltshire Council are procuring a contract for the delivery of the M4 Junction 17 improvement works, with a view to awarding the contract in early spring 2026. Scope of Works The proposed scheme includes: • Installation …
of traffic signals on all roundabout approaches • Carriageway widening throughout the junction • Increasing the number of traffic lanes across the motorway bridges from two to three • Widening of the circulatory carriageway The successful contractor must be capable of working on the National Highway
s network and experienced in delivering complex highway infrastructure improvements. Delivery Phases (estimated) The contract will be delivered in two phases: • Phase 1 – Early Contractor Involvement (ECI): Spring 2026 – Autumn 2026 • Phase