EnBW plans the installation of the OWF "He Dreiht" with 900 MW grid capacity with 64 locations in the German North Sea, approximately 90 km of the North Sea coast (70 Nm from Eemshaven). For the foundation and turbine i…
nstallation scope Client Representatives are required to witness the installation activities offshore. Foundation installation is planned from Q2 2024 onwards with a duration of approximately 95 days (p90). Turbine installation is scheduled from Q2 2025 onwards with a similar duration.
EnBW plans the installation of the OWF "He Dreiht" with 900 MW grid capacity with 64 locations in the German North Sea, approximately 90 km of the North Sea coast (70 Nm from Eemshaven). For the foundation and turbine i