- Estimated value
- 16,474,549 GBP
The Works will enable the provision of an import capacity of 25,000 kVA via two Grid Supply Points.
Installation of 33kV cables for approximately 8.5km route length and installation of a 33/11kV metering substation compr…
ises of 2 x 11kV incomer circuit breakers, 1 x 11kV bus section circuit breakers and 4 x 11kV metering circuit breakers.
UK Power Networks will install 1 x Grid transformer at King’s Lynn Grid an associated circuit breaker to connect the transformer.
UK Power Networks will manage 132kV and 33kV outa
ge and substation lease.
UK Power Networks will carry out 33kV final closing joints
UK Power Networks carries out all the Contestable and Non-Contestable Works.
CONTESTABLE WORK - Estimated Cost £9.7M
EHV Plant and Switchgear
• Primary Subs