- Type
- 11
- Procedure
- neg-w-call
- Ref. number
- 763286-2025
- Estimated value
- 50,000,000 EUR
- CPV
- 98391000
The contract shall include all the required work for the decommissioning of Balance of Plant (BoP) components for the Alpha Ventus Offshore Wind Farm. The scope of work for the BoP decommissioning shall comprise: • Disma…
ntling and transport to shore of all 12 WTG foundations (6 Jackets and 6 Tripods) as well as the OSS Jacket installed within Alpha Ventus OWF, including provision of required vessels, equipment, tools and personnel. o Option 1: Partial pile removal (mechanical separation of piles and supporting stru
cture). o Option 2: Full pile extraction (additional scope of complete pile removal by Vibrohammer or other extraction method). • Dismantling and transport to shore of the OSS Topside installed within Alpha Ventus OWF, including provision o