- Type
- 20
- Procedure
- neg-w-call
- Ref. number
- 28833-2025
- Estimated value
- 25,000,000 EUR
- CPV
- 45255800
The project involves the construction of a biogas plant in Finnsnes, Northern Norway, located adjacent to an existing waste-to-energy district heating facility. The plant will be designed to process approximately 65,000 …
tonnes of organic waste annually, including food waste, sewage sludge, fish waste, and similar feedstocks. The facility must produce biogas, with the final product being liquefied vehicle fuel. The selected contractor will be responsible for the design, engineering, construction, and commissioning o
f the biogas plant. The procurement process consists of several phases, starting with pre-qualification. It is recommended that suppliers interested in applying to participate begin by reading the uploaded documents "General Introduction" a